 |
|
|
Drainage & StormwaterComprehensive Plan Implementation Committee (CPIC)Goals, Objectives, Strategies |
| |
|
1.1 GOAL 1 : Prepare, at the earliest
possible date, and maintain, a Lafayette Parish Comprehensive
Drainage/Storm Water Plan 2.
Objective3
1.1.1. Complete a digital one foot contour elevation map of the
parish.
Potential Guidelines/Strategy 4
1.1.1.1 Organize a Drainage/Storm Water coordinating team of
local agencies directly impacted by parish drainage/storm water
needs, consisting of not more than seven people.
1.1.1.2 Prepare a scope of work to complete a digital one foot
contour and elevation map of the parish.
1.1.1.3 Secure funding through federal/state/local resources
within six months of December 2002.
1.1.1.4 LCG contracts with consultants not later than March 2002
for LIDAR 6' grid of parish and one foot contours with supporting
elevation data.
Objective
1.1.2 Complete a digital Hydrologic Model of the parish including
flow sources and results.
Potential Guidelines/Strategy
1.1.2.1 Drainage/Storm Water Coordinating Team prepares a scope
of work not later than July 2002.
1.1.2.2 Funding resources are identified to complete the
Hydraulic Model of the Parish.
1.1.2.3 Contract is signed not later than September 2002 with
consultant to complete a digital Hydraulic Model of the Parish
including flow sources and results.
Objective
1.1.3 Complete a digital Retention/Detention Model of the parish.
Potential Guidelines/Strategy
1.1.3.1 Drainage/Storm Water Coordinating Team prepares a scope
of work not later than March 2003.
1.1.3.2 Funding resources are identified to complete the digital
Retention/Detention Model of the parish.
1.1.3.3 Contract is signed not later than May 2003 with
consultants to complete a Retention/Detention Model of the parish.
Objective
1.1.4 Complete a Water Quality Analysis for the parish.
Potential Guidelines/Strategy
1.1.4.1 Drainage/Storm Water Coordinating Team prepares a scope
of work not later than June 2003.
1.1.4.2 Funding resources are identified to complete the digital
Water Quality Analysis for the parish.
1.1.4.3 Contract is signed not later than September 2003 with
consultants to complete a Water Quality Analysis for the parish.
Objective
1.1.5 Complete a Water Resource Management Plan for the parish.
Potential Guidelines/Strategy
1.1.5.1 Drainage/Storm Water Coordinating Team prepares a scope
of work not later than December 2003.
1.1.5.2 Funding resources are identified to complete the digital
Water Resource Management Plan for the parish.
1.1.5.3 Contract is signed not later than February 2004 with
consultants to complete a Water Resource Management Plan for the
parish.
Objective
1.1.6 The Lead Agency/Dept. should be selected not later than
February 2002 to develop, manage, and maintain Storm Water Plan and
fund related implementation throughout the parish.
Potential Guidelines/Strategy
1.1.6.1 Select one of the following potential entities for Storm
Water Plan implementation:
- Lafayette Consolidated Government (including
intergovernmental agreements with Broussard, Carencro, Duson,
Scott, and Youngsville)
- Lafayette Utilities System (LUS)
- Lafayette Council of Governments (a nonprofit corporation
coordinating among local elected officials through
intergovernmental agreements).
- Form a Lafayette Parish Storm Water District
- Bayou Vermilion District
1.1.6.2 Identify and approve "Storm Water Management"
as public utility service and apply monthly fees to all structures
throughout the parish based on an impervious surface formula.
1.1.6.3 Selected Storm Water Agency assumes responsibility for
parish stormwater plan, management and implementation not later than
June 2002.
1.1.6.4 Selected Storm Water Agency identifies revenue resources
to support implementation of Drainage/Storm Water Plan.
Objective
1.1.7. Prepare a five-year update of the Comprehensive Drainage
Plan beginning in 2010 and every five years thereafter.
Potential Guidelines/Strategy
1.1.7.1 Parish Storm Water Agency should update the Lafayette
Parish Comprehensive Drainage/Storm Water Plan in five year
increments beginning in 2010.
1.1.7.2 The parish Drainage/Storm Water Plan should be
coordinated and compatible with the adopted Comprehensive Plan for
Lafayette Parish: LINC.
1.1.7.3 Updates to the Drainage/Storm Water Plan should be funded
by the parish Storm Water Agency.
1.2 GOAL: Lafayette Parish should join the Community Rating System
(CRS) sponsored by the National Flood Insurance Program as soon as
possible. 5
Objective
1.2.1 Lafayette City-Parish Consolidated Government and the
municipalities of Broussard, Carencro, Duson, Scott and Youngsville
should join the Community Rating System (CRS) in the year 2003, at the
latest.
Potential Guidelines/Strategy
1.2.1.1 A planning grant application is to be prepared by the
Traffic and Transportation Department Planning Division to complete
a Comprehensive Hazard Plan for Lafayette Parish and its
municipalities. The Plan includes a CRS Flood Prevention Plan, as
well as other hazard plans such as hurricane, tornado, oil spill,
train wreck spills and other hazards determined to be significant.
This application is to be submitted not later than June 2002.
1.2.1.2 If the planning grant is successful and awarded, the
Comprehensive Hazard Plan is prepared and completed by August 2003.
The Plan preparation shall be coordinated by the Planning Division
of the Department of Traffic and Transportation working in
conjunction with the Public Works Department and the Office of
Emergency Preparedness.
1.2.1.3 If the planning grant application is not successful, then
the CRS Plan preparation proceeds for the Lafayette Consolidated
Government and parish municipalities by the Traffic and
Transportation Department Planning Division and proposed to be
completed by December 2003.
1.2.1.4 The CRS program is coordinated among the local
governments by one of the following agencies/departments:
- The Lafayette Council of Governments
- The designated Storm Water Management Agency for the Parish.
- A proposed Parish Drainage District
- The Codes Division of the LCG Department of Planning, Zoning
and Codes in cooperation with the Flood Plain Administrators for
the municipalities of Broussard, Carencro, Duson, Scott and
Youngsville.
- The Public Works Department of Lafayette Consolidated
Government in coordination with the municipalities of Broussard,
Carencro, Duson, Scott and Youngsville.
- The proposed Citizen Drainage Advisory Committee through the
City-Parish Planning Commission.
Objective
1.2.2 Achieve 1,000 CRS Credit Points (by performing program
activities) for each governmental jurisdiction within the first year
of participation.
Potential Guidelines/Strategy
1.2.2.1 Public Information Activities to include elevation
certificates, map information, outreach projects, hazard disclosure,
flood protection library, and flood protection assistance.
1.2.2.2 Mapping and Regulatory Activities to include additional
flood data, open space preservation, higher regulatory standards,
flood data maintenance, and storm water management.
1.2.2.3 Flood Damage Reduction Activities to include Flood Plain
Management Plan, acquisition, relocation and/or retrofitting of
habitually flooding structures as well as drainage system
maintenance.
Objective
1.2.3 Achieve 1,500 CRS Credit Points (by performing program
activities) for each governmental jurisdiction within the second year
of participation
Potential Guidelines/Strategy
1.2.3.1 Public Information Activities to include elevation
certificates, map information, outreach projects, hazard disclosure,
flood protection library, and flood protection assistance.
1.2.3.2 Mapping and Regulatory Activities to include additional
flood data, open space preservation, higher regulatory standards,
flood data maintenance, and storm water management.
1.2.3.3 Flood Damage Reduction Activities to include Flood Plain
Management Plan, acquisition, relocation and/or retrofitting of
habitually flooding structures as well as drainage system
maintenance.
Objective
1.2.4 Achieve 2,000 CRS Credit Points (by performing program
activities) for each governmental jurisdiction within the third year
of participation.
Potential Guidelines/Strategy
1.2.4.1 Public Information Activities to include elevation
certificates, map information, outreach projects, hazard disclosure,
flood protection library, and flood protection assistance.
1.2.4.2 Mapping and Regulatory Activities to include additional
flood data, open space preservation, higher regulatory standards,
flood data maintenance, and storm water management.
1.2.4.3 Flood Damage Reduction Activities to include Flood Plain
Management Plan, acquisition, relocation and/or retrofitting of
habitually flooding structures as well as drainage system
maintenance.
Objective
1.2.5. Achieve a 20% reduction on premiums paid by parish and
municipal holders of flood insurance policies through the National
Flood Insurance Program by the third year of participation in the CRS
program.
Potential Guidelines/Strategy
1.2.5.1 Acquisition and relocation of repetitive loss structures
should be focused and coordinated with open space and storm water
management.
1.2.5.2 Improved GIS flood data maintenance.
1.3 GOAL: Establish a permanent Citizen Drainage/Storm Water
Advisory Committee answerable to the City-Parish Planning Commission . 6
Objective
1.3.1 The City-Parish Planning Commission prepares rules of policy
and procedure for the establishment of the Citizen Drainage/Storm
Water Advisory Committee.
Potential Guidelines/Strategy
1.3.1.1 The primary purpose of this committee is to recommend to
the Commission on issues directly affecting the review, adoption
and/or amendments to the Drainage/Storm Water Element of the
Comprehensive Plan.
1.3.1.2 The secondary purpose of this committee is to recommend
to the City-Parish Planning Commission on related drainage/storm
water matters as requested by the Commission.
1.3.1.3 The tertiary purpose of the committee is to advise the
City-Parish Planning Commission on drainage and storm water items
that the committee, as citizens of the community, deem appropriate.
1.3.1.4 The actions of the committee are strictly advisory in
nature and are to be directed solely to the Planning Commission.
1.3.1.5 The committee may research, interview, study, analyze,
discuss, and otherwise deliberate on drainage/storm water issues
affecting Lafayette Parish and its municipalities.
1.3.1.6 The committee may not transmit formal communication on
opinions or recommendations on any matter other than that directed
to the Planning Commission.
1.3.1.7 Committee members are appointed and serve at the pleasure
of the sitting Planning Commission.
1.3.1.8 The Citizen Drainage/Storm Water Advisory Committee
should consist of no more than five individuals who may or may not
be members of the Planning Commission.
Objective
1.3.2 The Citizen Drainage/Storm Water Advisory Committee is
formally established by the City-Parish Planning Commission.
Potential Guidelines/Strategy
1.3.2.1 Resolution is adopted establishing the City-Parish
Planning Commission's Citizen Drainage/Storm Water Advisory
Committee.
1.3.2.2 The committee membership is appointed not later than
August 2002.
1.3.2.3 The administration of the Citizen Drainage/Storm Water
Advisory Committee shall be provided by the Planning Division of the
Department of Traffic and Transportation and the Department of
Public Works.
The Comprehensive Plan Implementation Committee has approved,
recommends and submits the above Implementation Strategies as an
initial priority need for the Drainage/Storm Water Element of the
Comprehensive Plan.
1.4 GOAL: Prepare a method of ranking drainage projects which
prioritizes expenditures based on objective ranked criteria. 7
Objective
1.4.1 The "Lead Agency" [as described in Potential
Guidelines/Strategy 1.1.6.1] is established and financed.
Objective
1.4.2 The Lead Agency establishes a mathematical formula which
ranks projects based on reduction of flooding within each drainage
area by evaluating market value of real estate/or structures and
giving priority to protecting residential structures as a first
priority; then business structures as a second priority; streets and
roadways as a third priority; and, finally undeveloped land as a
fourth priority.
Potential Guidelines/Strategy
1.4.2.1 The Lead Agency determines the method presently in use by
LCG and other local governmental jurisdictions (within Lafayette
Parish) to prioritize projects.
1.4.2.2 The Lead Agency evaluates current methods of drainage
project prioritization by:
- Examining methods of defining the boundaries of a targeted
area;
- Examining methods of evaluating a market value of
residential and business structures, streets, as well as
undeveloped land within a targeted drainage area.
- Examining methods of ranking the market value of
a. residential structures
to
b. business structures to
c. streets to
d. undeveloped land
within a targeted drainage area.
1.4.2.3 The Lead Agency modifies the current method of evaluating
and ranking the priority of drainage projects so that the following
relationships are true:
- The definition of a project rating percentage factor is
defined as:
A = Rating
Percentage 1
B = Rating
Percentage 2
C = Rating
Percentage 3
D = Rating
Percentage 4
- The definition of ranking relationships between project rating
percentage factors is:
Rating Percentage 4
< Rating Percentage 3 <
Rating Percentage 2
< Rating Percentage 1
The project rating percentages are to be determined by the
stakeholders. 8
- A project rating percentage factor is not greater than
100.00%.
- A drainage area is defined as the enclosed geographic area
within a continuous boundary within which the stormwater flows.
Typically, stormwater travels through a critical passage or
point at which the stormwater is being presently impeded and
thus causes flooding within the drainage area.
- The critical passage or impeded point is the structure that
should be made larger or altered in order to prevent localized
flooding.
- The component values evaluated within a project target area
are defined as:
RES Value = the total market value of residential
structures
BUS Value = the total market value of business structures
RD Value = the estimated present value of total
construction costs of streets and roadways flooding during a
100-Year Flood 9
UNDEV Value = the total market value of undeveloped land
within a project target area
- The total evaluated value (TEV) of all structures within a
project target area is defined as:
TEV = (A x RES Value) + (B x BUS Value) + ( C x RD Value) + (D x
UNDEV Value)
1.5 GOAL: Define existing and future flooding problems so that the
effects of the Comprehensive Drainage/Storm Water Plan can be measured. 10
Objective
1.5.1 The MPO/Planning Division creates an inventory of residential
and business structures, undeveloped land as well as roadways that
have flooded on or before July 4, 2000, and thus creates a data set
which is defined as "Existing." "Future" flooding
problems are defined as those occurring after this date.
Potential Guidelines/Strategy
1.5.1.1 The Comprehensive Planning/MPO Division in conjunction
with Federal Emergency Administration (FEMA) identifies and
digitally maps the 100-Year Flood Zone within Lafayette Parish.
1.5.1.2 The Comprehensive Planning/MPO Division in conjunction
with Federal Emergency Administration (FEMA) identifies and
digitally maps "multiple flooding event residential
structures" for which NFIP claims of more than $1,000 have been
filed more than once and for which more than one claim was made on
or prior to the middle of 2000 on or about July 4.
1.5.1.3 Stakeholders in the Department of Transportation and
Development (DTT) inventory roadways susceptible to flooding during
100-year Flood on or prior the middle of 2000 on or about July 4.
1.5.1.4 Stakeholders in the Department of Transportation and
Development (DTT) inventory approved roadways which are designed to
function as retention and detention facilities during periods of
high rainfall. These roadways were built or approved by other local
governmental jurisdictions, LCG itself, or one of its predecessors,
particularly the Lafayette Parish Police Jury, the Lafayette Parish
Government, and the City of Lafayette.
1.5.1.5 The CRS program stakeholders [as developed in Section
1.2.1.4] request the release of information from the LCG Request For
Services System pertaining to flooding and drainage. The information
requested is: (1) The name and address of the person requesting
services; (2) The date of the request; and, (3) A description of the
drainage problem.
1.5.1.6 The information and maps from the Request for Services
are integrated with the information received from FEMA information
on habitually flooded structures (produced in Potential
Guidelines/Strategy 1.5.1.1) and with the information developed by
Department of Transportation and Development Stakeholders on
roadways susceptible to flooding during a 100-Year Flood (as
described above in Potential Guidelines/Strategy 1.5.1.4).
1.6 GOAL: Mitigate existing, as well as future flooding, in
residential structures, business structures, roadways not designed to
act as retention and detention, as well as undeveloped land. Priority in
conducting analysis and funding projects should be given to residential
structures first, then business structures, then to roadways not
designed to function as retention and detention facilities, and finally
to undeveloped land. 11
Objective
1.6.1 The Lead Agency [identified in Objective 1.4.1] performs a
drainage analysis using the formulas described [in Goal 1.4]. 12
Potential Guidelines/Strategy
1.6.1.1 Utilizing the flood event maps and databases [developed
in Goal 1.5], the Lead Agency identifies the drainage areas in which
clusters of flood events have occurred including residential and
business structures, as well as undeveloped land or roadways not
designed to function as retention or detention facilities.
1.6.1.2 The Lead Agency evaluates all of the drainage areas
identified in the previous Potential Guidelines/Strategy using the
criteria described [in Objective 1.4.1].
1.6.1.3 The Lead Agency ranks the drainage areas identified in
the previous Potential Guidelines/Strategy using the Total Evaluated
Value (TEV) [as defined in Potential Guidelines/Strategy 1.4.1.4]
1.6.1.4 The Lead Agency identifies the causes 13
of flooding within each drainage area in the above Potential
Guidelines/Strategy as either localized or systemic. 14
Flooding is localized when the capacity of the drainage area
(as defined in Potential Guidelines/Strategy 1.4.1.4.) is not
fully utilized in 100-Year Flood 15
such that some portions of the drainage facilities are operating
at less than full capacity and other portions of the drainage
facilities are operating at beyond their capacity. Typically,
localized flooding also occurs in conjunction with an impediment
which reduces capacity in the drainage facilities. When the
impediment is cleared or capacity is increased at single or
multiple points, then the capacity of the drainage facilities is
not overwhelmed with more stormwater than can be handled.
Systemic flooding on the other hand occurs when the capacity of
the drainage facilities in a drainage area during a 100-Year Flood
is overwhelmed. The solution to systemic flooding is not an
increase in capacity at single or multiple points along a drainage
facility, rather, an increase in capacity along the entire
drainage facility within a drainage area during a 100-Year Flood.
Localized flooding tends to be the result of private efforts
while systemic flooding tends to be the result of government
efforts to regulate stormwater. Examples of localized flooding are
found when: (1)property owners utilize undersized, concrete
reinforced pipe on their property; (2) property owners change a
governmentally approved open ditch on their property to an
enclosed drainage facility; or, (3)owners of undeveloped property
change the existing natural course of a drainage facility across
their property. Examples of systemic flooding are found when:
(1)governments improve or create drainage facilities that
historically handled 100-Year Floods, but, due to urban
development, no longer can handle a 100-Year Flood; or,
(2)developers create drainage facilities which received
governmental approval, but can no longer handle 100-year Flood due
to urban development.
If flooding is found to be due to localized causes, then the
identified party is responsible for the solution to the flooding
problems. The solution must be approved by the Stakeholders.
Flooding may be attributable to systemic causes wherein local
governmental jurisdictions are responsible for the construction or
approval of the drainage facility. If local governmental
jurisdictions located within the parish or their predecessor
agencies (i.e., Lafayette Parish Police Jury, City of Lafayette,
etc.) are responsible for the solution to the flooding problems,
then those local governmental jurisdictions are responsible. If
the problem is systemic wherein other governmental agencies (state
or federal agencies, etc.) hold jurisdiction, then that agency is
responsible for the solution.
1.6.1.5 The Stakeholders shall review and recommend solutions to
the flooding causes in the drainage areas to the lead agency such
that:
- The solutions would mitigate flooding within the drainage area
for a 100-Year Flood.
- The solutions would mitigate downstream flooding outside of
the drainage area for a 100-Year Flood.
- The solutions are integrated and complimentary to the goals,
objectives, and strategies in the Comprehensive Drainage/Storm
Water Plan [as described in Goal 1.1]
- Roadways designed to act as retention and detention facilities
are not scheduled for drainage improvements if the existing
flooding is confined to periods of a 100-Year Flood.
Objective
1.6.2 The Lead Agency encourages and mandates participation in the
National Flood Insurance Program (NFIP) such that:
Potential Guidelines/Strategy
1.6.2.1 The stakeholders responsible for the CRS program
implementation are identified [and described in Potential
Guidelines/Strategy 1.2.1.4] as the parish-wide entity which
coordinates local government participation in the CRS program.
1.6.2.2 The CRS stakeholders recommend modifications to the local
flood zone ordinances to include the following changes required by
the implementation of LINC:
- Property owners of flooding structures are required to
purchase NFIP insurance if: (1)there have been two NFIP
insurance claims since the institution of the federal program;
and, (2)the cost of each claim separately has been in excess of
$1,000.16
- Property owners of flooding residential and commercial
structures may apply for local, state, and federal funds to
elevate their structures or to sell their structures to the Lead
Agency for demolition and removal if (1)there have been two NFIP
insurance claims since the institution of the federal program
and (2)the cost each claim separately has been in excess of
$1,000.17
- Habitually flooding structures are to be condemned if there
have been three flooding events within 5 years with separate,
individual NFIP claims in excess of $1,000.18
- Structures built in the 100-Year Flood Plain are required to
have a flood elevation certificate with a floor elevation of 12
inches or greater than the 100-year flood elevation19
of a particular building site.20
- Structures built above the100-Year Flood Plain are required to
have a floor elevation of 12 inches or greater than the 100-year
flood elevation of a particular building site based on the
approved one foot contour map as described in Section 1.1 21
- The design of the pre-development and post-development
stormwater runoff system from a site with a LCG or other local
government (participating in the drainage/stormwater plan)
building permit shall seek to be equal to a 100-Year Flood.22
- The developer's engineer23shall
design hydraulic structures and retention systems for no
increase in storm water runoff water quantity in excess of a
100-Year Flood from a building site.
- The developer's engineer shall determine and certify:
(1) an amount of an impact fee (using schedules adopted by LCG)
equal to the construction and long-term maintenance of a
retention and/or detention facility within the drainage area of
said site equal to a 100-Year Flood or the portion thereof which
is not detained/ retained on site; and/or,
(2) the size and performance of an onsite retention and
detention facility required for a 100-Year Flood. The facility
is to be constructed to be integrated into the Comprehensive
Drainage/Storm Water Plan [as described in Goal 1.1].24
- The drainage performance existing as a result of the
implementation of the Comprehensive Drainage/Storm Water Plan is
perpetual. If the site ceases to perform as approved and the
site has not been modified, then the responsibility shall be the
responsibility of the Lead Agency. If however, the site ceases
to perform as approved and the site has been modified, then the
responsibility for reestablishing drainage performance shall be
the responsibility of the property owner.
Likewise, the drainage conditions as approved by LCG or other
local government (participating in the drainage/stormwater plan)
upon platting and receiving building permits shall be perpetual.
If the site ceases to perform as approved and the site has not
been modified, then the obligation shall be the responsibility
of the Lead Agency. If however, the site ceases to perform as
approved and the site has been modified, then the obligation for
reestablishing approved conditions shall be the responsibility
of the property owner.25
- The advisory entity [created in goal 1.3], while acting in due
process, shall determine the responsibility of flooding events
and shall duly report their findings to the Lafayette
City-Parish Planning Commission. A private landowner found to be
liable for the flooding may present engineering or hydrological
evidence supporting any counter claims when each report of
findings is submitted to a body.26
1.6.2.3 The CRS stakeholders apply annually and during periods of
special allocations (resulting from hurricanes or other storm
events) to the Louisiana Office of Emergency Preparedness as well as
other sources for grants to elevate or purchase habitually flooding
structures.27
1.6.2.4 Using the information and maps [as described in the
Potential Guidelines/Strategy 1.2.1.4], the CRS stakeholders
identify the owners of inhabitable residential and business
structures as well as undeveloped land that have flooded once,
twice, or more.
1.6.2.5 The individuals identified in the previous Potential
Guidelines/Strategy are notified of the changes in the LCG flood
plain ordinance [as described in Potential Guidelines/Strategy
1.6.2.2].
1.7 GOAL: Institute a maintenance plan for drainage facilities so
that the designed or natural performance capacity is maintained.28
Objective
1.7.1 The Lead Agency [as described in Potential
Guidelines/Strategy 1.1.6.1] of the Comprehensive Drainage/Storm Water
Plan develops a maintenance program for existing and new drainage
facilities. See Illustration 1.7.
Potential Guidelines/Strategy
1.7.1.1 The Lead Agency, seeks approval for a bond issue for the
construction and maintenance of facilities constructed and
maintained as part of the Comprehensive Drainage/Storm Water Plan
[and further described in Goal 1.1]
1.7.1.2 The monthly drainage utility revenues [as described in
Potential Guidelines/Strategy 1.1.6.2] are dedicated to a Drainage
Construction Fund for the sole purpose of payment of the drainage
bond issues to implement the Comprehensive Drainage/Storm Water
Plan.
1.7.1.3 The revenues collected from drainage impact fees [as
described in Potential Guidelines/Strategy 1.6.2.2.7] are paid into
the Drainage Construction Fund for the sole purpose of
payment of the drainage bond issues to implement the Comprehensive
Drainage/Storm Water Plan.
1.7.1.4 The Drainage Construction Fund receives revenues from
three sources: (1) project impact fees, (2) drainage utility fees,
and (3) fund transfers from the Drainage Replacement Fund [as
described in Section 1.7.1.6]. The revenues from impact and utility
fees are used to fund the drainage bond issue. The revenues from the
Drainage Replacement Fund are used for emergency payments in cases
of potential default on the bond issue.
1.7.1.5 Beyond collection of revenues for the financing,
construction, and engineering costs, an additional percentage of the
revenues is collected, set aside, and dedicated solely for
maintenance of existing facilities which over time require work to
preserve designed capacity. This fund shall be known as the Drainage
Maintenance Fund.29
1.7.1.6 Beyond collection of revenues for financing,
construction, and engineering costs, an additional percentage of the
revenues are collected, set aside, and dedicated solely for the
replacement of existing facilities which overtime will degrade and
need reconstruction. This fund shall be known as the Drainage
Replacement Fund.
1.7.1.7 Beyond collection of revenues for financing,
construction, and engineering costs, an additional percentage of the
revenues are collected, set aside, and dedicated solely for the
elevation or purchase of structures that have flooded three or more
times in five years. This fund shall be known as the Elevation
and Buyout Fund.30
1.7.1.8 Unused portions of the Drainage Construction Fund,
the Drainage Maintenance Fund, the Drainage Replacement
Fund, and the Elevation and Buyout Fund are each invested
every six (6) months in separate accounts which (1)have the full
faith and credit of the US government and (2)are liquid within 6
months with no loss of principal.
1.7.1.9 In even numbered years on or about the first working day
after Veteran's Day, an evaluation is made of the Drainage
Replacement Fund and the Elevation and Buyout Fund to
determine if fund transfers are necessary such that a portion of the
Buyout and Elevation Fund is transferred to the Drainage
Replacement Fund. The amount of the transfer is to be determined
by the advisory committee [as defined in Objective 1.3.1] in concert
with the Comprehensive Plan Implementation Committee.
1.7.1.10 Every four years on or about the first working day after
Veteran's Day, an evaluation is made of the Drainage Maintenance
Fund and Drainage Replacement Fund to determine if fund
transfers are necessary such that the portion of the Drainage
Maintenance Fund is transferred to the Drainage Replacement
Fund. The amount of the transfer is to be determined by the
advisory committee [as defined in Objective 1.3.1] in concert with
the Comprehensive Plan Implementation Committee.
1.8 GOAL: Limit use of roadways during periods of high rainfall.
Objective
1.8.1 Inventory roadways which have flooded during periods of high
rainfall.31
Potential Guidelines/Strategy
1.8.1.1 Department of Traffic and Transportation stakeholders
utilize the map which identifies and maps roadways susceptible to
flooding during 100-Year Flood [as described in Strategies 1.5.1.3
and 1.5.1.4].
1.8.1.2 Department of Traffic and Transportation stakeholders
install appropriate signage along roadways identified as susceptible
to flooding such that:
Objective
1.8.2 Install signage on roadways which have flooded during periods
of high rainfall.
Potential Guidelines/Strategy
1.8.2.1 Department of Traffic and Transportation stakeholders
install appropriate signage along roadways identified as susceptible
to flooding such that:
1) The roadway is identified to motorists and pedestrians as
susceptible to flooding during 100-Year Flood.
2) The range of flooding is marked on sign post showing the
highest and typical level of flooding that occurs within the right
of way.
|
|
Back to top
|
|
X:\11020_DRAIN_CPIC\001_Goal_Obj_Strategy\strategy_final.wpd
Page Last Revised on 2/1/2002
|
|
|
 |
Sidenotes |
-
A goal is a general statement
of a future condition which is considered desirable for the
community; it is an end towards which actions are aimed.(back)
-
The Steering Committee, after due
consideration of reports from its Drainage Subcommittee and staff,
proposed in Recommendation 16 that: "The absolute urgent need
for a comprehensive drainage plan for the parish at the earliest
possible date". The CPIC Drainage Subcommittee Response
reviewed the original proposal and modified such that: "Due to
its urgent need as a priority for the comprehensive plan, a
comprehensive drainage and stormwater plan must be completed as soon
as possible". (back)
-
An objective is a statement of a
measurable activity to be accomplished in the pursuit of a goal; it
refers to some specific aspiration which is reasonably attainable. (back)
-
A potential guideline is a suggested
proposal to do something that relates directly to accomplishing the
objective; it identifies the how, where, and amount which may be
done. As per CPIC action on September 16, 2001, it was determined
that CPIC as a body would suggest "Potential
Guidelines/Strategy" as opposed to mandating
"strategies" when assigning Comprehensive Plan initiatives
for stakeholder implementation. (back)
-
The Steering Committee, after due
consideration of reports from its Drainage Subcommittee and staff,
proposed in Recommendation 3 that: " Lafayette Parish should
join the Community Rating System (CRS) sponsored by the National
Flood Insurance Program as soon as possible" . The CPIC
Drainage Subcommittee responded that "Lafayette Parish should
join the Community Rating System (CRS) sponsored by the National
Flood Insurance Program and aggressively participate in the benefits
of its grant programs and insurance rate reduction
opportunities." (back)
-
The Steering Committee, after due
consideration fo reports from its Drainage Subcommittee, proposed in
Recommendation No.1 that LCG should "Establish a permanent
Citizen Drainage Advisory Committee answerable to the City-Parish
Planning Commission." The CPIC Drainage Subcommittee responded
that LCG should "Establish a permanent Citizen Drainage/Storm
Water Advisory Committee answerable to the City-Parish Planning
Commission". (back)
-
Recommendation No. 2 from the
Steering Committee, after due consideration from its Drainage
Subcommittee, stated "... members ranked the term
"flooding problems" for priority concerns and ...
recommend solutions." Ranked in terms of priority were "(1st)
Residential Units, (2nd) Business Buildings, (3rd)
Street/Roadways and (4th) Land (Vacant, Agricultural,
Yard)". (back)
-
s used in the Comprehensive
Drainage/Storm Water Plan, the Lead Agency [as described in Section
1.1.6.1] is different from the stakeholders. The Lead Agency is the
local governmental group which has the primary responsibility to
implement the drainage/stormwater plan. The stakeholders are
generally composed not only of members from the Lead Agency, but
also other additional participants in the drainage/stormwater plan.
These other participants have a stake in the success of the plan and
as such participate in the formulation of policy and implementation
of strategies.When a particular group of
stakeholders are identified as significant, then that group is
particularly identified as in Section 1.5.1.3 when reference is made
to the Department of Traffic and Transportation stakeholders. (back)
-
The definition of a 100 Year Flood
used in this drainage/stormwater plan is the one used by the Federal
Emergency Management Agency (FEMA). According to the Federal
Emergency Agency , "The term "100-year flood" is
misleading. It is not the flood that will occur once every 100
years. Rather, it is the flood elevation that has a 1- percent
chance of being equaled or exceeded each year. Thus, the 100-year
flood could occur more than once in a relatively short period of
time. The 100-year flood, which is the standard used by most Federal
and state agencies, is used by the NFIP as the standard for
floodplain management and to determine the need for flood
insurance." See the world wide web internet site as configured
on March 1, 2001: http://www.fema.gov/.. (back)
-
The original LINC Steering Committee
stated in Recommendation 2 that two terms were used to classify
flooding problems. Existing flooding problems are those which occur
"... assuming there would be no further development in the
parish (roads, houses, businesses, industry, etc)". In
distinction, future flooding problems are those which occur "
... assuming new development in the parish will continue (with new
roads, houses, businesses, and industry)". The committee was
meeting then in the Summer of 2000 so that the approximate mid-point
in the summer, (i.e. July 4th) was established as the
benchmark between existing and future problems. (back)
-
Goal 1.6 is taken from 8 separate
recommendations: 5, 6, 7, 8 , 9, 10, 11, and 12 as described in the
chart below. Recommendations 5, 6, 7, and 8 deal with existing,
repeat flooding while 9, 10, 11, and 12 deal with future, first-time
flooding. Likewise, Recommendations 5 and 9 deal with residential
structural flooding issues. Recommendations 6 and 10 deal with
business structures flooding issues. Recommendations 7 and 11 deal
with roadway flooding issues. Recommendations 8 and 12 deal with
undeveloped lands. Many of the requirements are analogous as well
and are described in subsequent footnotes.
Time Period | Existing | Future |
Residential | Recommend. 5 | Recommend. 9 |
Business | Recommend. 6 | Recommend. 10 |
Roadway | Recommend. 7 | Recommend. 11 |
Undeveloped | Recommend. 8 | Recommend. 12 |
(back)
-
According to the Steering Committee
Recommendations 5, 6, 8 , 9 10, and 12, "An LCG drainage
analysis should be conducted for existing and future flooding
problems for residential and commercial structures as well as
undeveloped land." Recommendations 7 and 11 state that roadways
"if not designed for retention/detention facilities, (then) a
LCG drainage analysis should be conducted." (back)
-
Steering Committee Recommendations 5,
6, 7, 9, 10, 11, and 12 required that "causes identified (by an
LCG drainage analysis) must be cured by (the) responsible party if
found to be localized". The only recommendation which does not
require an identification of causes is recommendation 7 which deals
with existing roadways that have flooded in the past. Thus, all
types of flooding, except this narrow exemption for existing
roadways, require the identification of causes including existing
and future flooding in residential and commericial structures as
well as undeveloped land. (back)
-
The concept of localized flooding is
not explicitly defined in the formal recommendations; hence this
discussion defines localized flooding (and its conceptual opposite -
systemic flooding) based on: (1)notes taken during Steering Drainage
Subcommittee meetings during March, 2000; and, (2)illustrations of
localized flooding in the commentary attached to Recommendation 17
(i.e. " As an example (of localized flooding problems) streets
and roads designed as ‘open ditch’ are being compromised by
individual, haphazard subsurface installations of culverts". (back)
-
In the commentary of Recommendation
13, the Steering Committee approved the statement that " The
100-year flood event is a practical design standard for this area of
Louisiana considering that such a rain event is occuring not once
every 100 hundred years, but more realistically every ten
years." Additionally, listed in Recommendation 14, a 100-Year See footnote in section 1.4.2.3.7 for a discussion of
100-Year Floods. (back)
-
Steering Committee Recommendations 5,
6, 9, and 10 require "Mandatory Federal Flood Insurance after
the second event" for existing and future flooding events in
both residential and commerical structures. (back)
-
Steering Committee Recommendations 5
and 6 for existing residential and commerical structures state:
(1)"Elevate structure - 1st utilizing grant funding
and 2nd utilizing LCG resources" and (2) "Buy
Out Option - 1st utilizing grant funding and 2nd
utilizing LCG resources". Data for habitual flooding from FEMA
is readily available if these two limiting conditions are specified. (back)
-
Steering Committee Recommendations 5
and 6 for existing residential and commerical structures urge
"Condemnation /Demolition with three documented flooding events
within five years". FEMA data is readily available for claims
over $1,000, thus the addition of this limiting condition. (back)
-
The defintion of the Base Flood
Elevation (BFE) used in this drainage/stormwater plan is the one
used by the Federal Emmergency Management Agency (FEMA). According
to FEMA, the Base Flood Elevation (BFE) is "the elevation shown
on the Flood Insurance Rate Map (FIRM) for Zones AE, AH, A1-A30, AR,
AR/A, AR/AE, AR/A1-A30, AR/AH, AR/AO, V1-V30, and VE that indicates
the water surface elevation resulting from a flood that has a 1
percent chance of equaling or exceeding that level in any given
year". See the world wide web internet site as configured on
March 1, 2001: http://www.fema.gov/.. (back)
-
Steering Committee Recommendation 13
states "The Base Floor Elevation of all new structures should
be constructed a minium of six inches (6") above the 100 Year
federal flood hazard area (i.e by context, above the 100-Year Flood
Zone Base Flood Elevation) as determined at the time of
construction." Additionally, "A ‘Certificate of
Elevation’ will be required only in the Flood Hazard Area".
CPIC Drainage Subcommittee eventually recommended this standard be
set at 12 inches (12") above the Base Flood Elevation of a
100-Year Flood. (back)
-
Steering Committee Recommendation 13
states "... all new structures constructed outside the current
Flood Hazard Area (i.e by context, above the 100-Year Flood Zone
Base Flood Elevation) shall be elevated six inches (6") above
grade level as a future flood prevention measure." No flood
elevation certificate is required in areas above the 100 year flood
elevation as discussed in the previous footnote. CPIC Drainage
Subcommittee eventually recommended (1) this standard be set at
twelve inches (12") above the Base Flood Elevation of a
100-Year and (2) use the one foot contour map as a method of
determining the elevation of a site. (back)
-
Steering Committee Recommendation 14
uses "...100-Year Storm Flood" as a design criteria for
" ... all new development plats and plans that result in water
runoff exceeding the pre-development condition". (back)
-
The developer’s engineer is
required to have a professional engineer’s licence in civil
engineering or other appropriate engineering discipline in order to
approve construction drawings. (back)
-
Steering Committee Recommendation No.
14 states that "all new development plats and plans that result
in increased water runoff exceeding the pre-development condition
shall be required to mitigate the increase through ... two qualified
options: (1) Construction of a retention facility that maintains the
pre-development runoff; [or] (2) payment of an equivalent amount of
funds to a public funded Drainage District(s) to construct and
support a local area wide retention facility established for that
purpose". (back)
-
Steering Committee Recommendation 17
states that "Enforcement of existing and future drainage
regulations must be consistent and strengthened and follow a due
process." (back)
-
See Section 1.6.1.4 for discussion of
individual responsibility of landowners and Section 1.6.2.2 directly
above for requirements of due process. (back)
-
Steering Committee Recommendations 5
and 6 describing actions for existing residential and commercial
structures provide for elevation, condemnation, purchase, and/or
demolition of structures first utilizing grant funds and then
Comprehensive Drainage/Storm Water Plan resources. Such resources
are described in Goal 1.7. (back)
-
Steering Committee Recommendation 15
states "all existing drainage ways should be under a regular
and comprehensive maintenance program based on their designed or
natural performance capacity and function." (back)
-
In order to assure "a regular
and comprehensive maintenance program" as described in Steering
Committee Recommendation 15, additional revenues beyond those used
for construction, engineering, and financing is required for
maintenance and replacement of the system. The use of maintenance
and replacement funds is a modeled after a standard component of
United States Department of Agriculture - Rural Development grants
for sewer and water projects.
Assuming a 40 year loan at 5.0% interest
for a principal of $1,000,000, the annual payment of accumulated
interest and principal is equal to $58,300 per year.
The sum of the set aside funds for the Drainage
Maintenance Fund, Drainage Replacement Fund, as well as the
Elevation and Buyout Funds can be estimated at 22% or $12, 800 of
$58,300 per year project. Thus, if we add this $12,800 figure to the
$58,300 figure cited above yields a total cost of $71,100 per year
for each $1,000,000. At present, there are approximately 71,000
inhabited households in the parish. If we distribute this cost
evenly, then the cost to each household is about $1.00 per year for
each $1,000,000 of proposed projects.
The additional 22% for the financing funds will
generate approximately $1,000,000 in savings over a 40 year period
with a 3% return on the investment above inflation. Thus, the
additional 22% will provide funds equal to the original construction
cost plus inflation to be used for system replacement, maintenance,
and buyouts.
Thus, these complex
financing calculations can be simplified by saying that for each
$1,000,000 of projects financed and constructed, the average cost
per household in the year 2000 is about $1.00 per year. Assuming
conservative rates of financing and investment, this amount will not
only pay for project construction, but also for maintenance,
buyouts, and system replacement. (back)
-
A reliable source of funding is
required for provisions of the buyout and elevation options
discussed in Potential Guidelines/Strategy 1.6.2.2 and the purchase
habitually flooding property that is condemned and purchased by LCG
in Potential Guidelines/Strategy 1.6.2.2.See
the previous footnote for financing calculations. (back)
-
Steering Committee Recommendation 7
mandates (1) an inventory that roadways "designed to be used as
retention/detention facilities during high rainfall events". (back)
-
Steering Committee Recommendation 7
mandates "appropriate signage should be installed on these
streets/roads with ‘No Traffic’ identified above set flood
level/stages". (back)
|
Back to top |
|
 |